Planning Case Study 134
137 West Bar, Sheffield
Planning scenario(s)
Heritage assets affected
Non-designated heritage assets with archaeological and historic interest
Type of application & broad category
Local planning authority
Authority: Sheffield City Council
References: 06/04556/FUL
Development proposal
Erection of 4/5/6 storey building for mixed-use development including 46 residential units, office space, retail unit and associated car parking.
Archaeological information known about the site before the planning application was made, or before the development commenced, as appropriate
Nothing recorded was on the HER for the development site.
Archaeological/planning processes
A desk-based assessment revealed that a pair of steel cementation furnaces for the production of blister steel had been constructed on the West Bar frontage of the site by 1775, and were probably the furnaces of Samuel Shore, shown on a 1737 illustration of Sheffield. Shore’s furnaces were first recorded in 1717 and were probably the first built in the town.
This planning application was first proposed in 2006 and approved in May 2007. However, part 2 of the pre-commencement archaeological condition was not fulfilled until late 2017. The following is a summary of the events and milestones during that period:
- Archaeological investigations were undertaken in 2008 and revealed a well-preserved early crucible furnace. The foundation design for the development was subsequently revised to protect the furnace in situ;
- The developer then went out of business;
- Much later, a new developer took over the development, which was amended;
- The post-excavation assessment report of the archaeological investigation in 2008 was produced in 2015. This recommended that some further works should be undertaken (mainly metallurgical analysis) to be included in a final report;
- The new developer argued that there was no need to do this but the LPA confirmed that it was a requirement of the planning condition. This has two parts - the second part requires that "the development shall only take place in accordance with the approved WSI and the development shall not be brought into use until the Local Planning Authority has confirmed in writing that the requirements of the WSI have been fulfilled or alternative timescales agreed." The developer wanted to proceed with the development, but it was made clear that, if the archaeological work was not completed, enforcement might prevent use of the development;
- The eventual way forward to resolve the issue was for the developer to enter into an agreement with the archaeological contractor to complete the outstanding archaeological work, including paying in advance. The developer was thus able to use the property and the work was undertaken by the archaeological contractor.
Without the threat of enforcement, this successful outcome might not have happened. The early crucible furnace is now preserved under the development.
Outcomes: archaeological
The pre-commencement condition (part 1) allowed for the investigation of the cementation crucibles (which are of at least regional significance) and their preservation through redesign of the development.
The fact that Part 2 of the archaeology condition was not discharged by the LPA resulted in the second developer providing the necessary funding to complete the scientific analysis of the regionally important steel cementation crucibles.
References and links/bibliography
- ARCUS 2006, Archaeological Desk-Based Assessment of 137 West Bar, Sheffield. Unpublished report, ARCUS Report no. 1037.1
- Oxford Archaeology North 2015, Furnace Hill, West Bar, Sheffield, South Yorkshire: Archaeological Excavation Assessment Report. Unpublished report.
- Gregory R.A. and R.G. Mackenzie, ‘Archaeological analysis of a mid-19th- century steel crucible furnace from Sheffield’, Historical Metallurgy (forthcoming).